一、 水泥復(fù)合板活動(dòng)房搭拆方案
本工程職工宿舍和辦公均搭設(shè)臨時(shí)活動(dòng)房二層。搭設(shè)前按總平面布置選址,做好基礎(chǔ)的整平、夯實(shí),鋪150碎石墊層,上澆C20砼150厚,四周設(shè)200×200排水溝。由專(zhuān)業(yè)安裝單位安拆,項(xiàng)目部管理。其技術(shù)措施必須做好以下各方面。
First, take the cement board house demolition program activities
The engineering staff quarters and office erection of temporary activities are two-story house. Before erection site by the general layout, good foundation leveling, compaction, laying of 150 hardcore, 150 thick concrete poured C20, 200 × 200 located around the drain. An installation by a professional demolition unit, the project managed by the Department. The technical measures necessary to do the following.