1、工程概況:
東華理工學(xué)院南昌校區(qū)位于南昌市新城區(qū),該項(xiàng)目由東華理工學(xué)院投資、北方設(shè)計(jì)研究院設(shè)計(jì),建筑面積9811平方米,總高度26.3米的三層建筑物。1F為綜合訓(xùn)練場、健身房、乒乓球館,2F為輔助用房,3F為觀眾廳和比賽廳。
本安裝工程包括電氣(強(qiáng)電和弱電)、生活給排水、消防、防排煙工程。給水系統(tǒng)由校區(qū)給水網(wǎng)直接供水。主要包括:生活給排水、消防栓等。室內(nèi)給水熱水用PP-R管、冷水用PP-B管熱熔連接,排水管采用U-PVC管,消防管采用焊接鋼管焊接連接,本工程的電氣安裝包括強(qiáng)電和弱電,強(qiáng)電包括:動(dòng)力和照明、電氣設(shè)備安裝及防雷接地系統(tǒng)安裝。弱電包括:電話及綜合布線系統(tǒng)、有線電視系統(tǒng)、監(jiān)控系統(tǒng)、廣播系統(tǒng)和火災(zāi)自動(dòng)報(bào)警及聯(lián)動(dòng)等,諸多系統(tǒng)體現(xiàn)了大型現(xiàn)代化智能建筑功能齊全,自動(dòng)化程度高的特點(diǎn)。該工程的各樓層房間均設(shè)置機(jī)械通風(fēng)及排煙系統(tǒng)。
電氣弱電工程包括:綜合布線及消防報(bào)警。
2、施工部署及項(xiàng)目機(jī)構(gòu)組織
2.1、施工部署:
根據(jù)本工程的特點(diǎn),安裝工程合理安排施工人員, 按照“先下后上,先主管后支管,先干線后支線,先預(yù)制后安裝”的原則,實(shí)行平面分區(qū)、立體交叉作業(yè)的流水施工。為了給裝修及其他專業(yè)分包施工提供作業(yè)面,特別是水磨石地面施工前,安裝工程必須完成地面管線敷設(shè)、穿樓板的管道安裝及吊頂內(nèi)安裝施工等內(nèi)
1, Project Overview:
East China Institute of Technology campus is located in Nanchang, Nanchang new city, the project investment by the East China Institute of Technology, Design and Research Institute in northern design, construction area of 9811 square meters, total height of 26.3 m three-storey structure. 1F for the comprehensive training field, gymnasium, table tennis hall, 2F for the auxiliary building, 3F for the audience hall and games room.
The installation work, including electrical (electric and electronic), life water supply and drainage, fire, smoke control engineering. Water supply system directly from the campus water supply network. Include: life, water supply and drainage, fire hydrants, etc.. Indoor Water Supply PP-R pipe with hot water, cold water pipe with the PP-B melt connection, drainage pipe U-PVC pipe, fire tube welded steel pipe welded connection, the works of electrical installation, including electric and electronic, high power, including : power and lighting, electrical equipment installation and installation of lightning protection and grounding systems. Weak include: telephone and cabling system, cable TV systems, monitoring systems, broadcast systems and automatic fire alarm and so on, many systems reflects the large modern intelligent building full-featured, high degree of automation features. Rooms on each floor of the project are set to mechanical ventilation and smoke extraction system.
Weak electrical engineering including: cabling and fire alarm.
2, construction and project institutions and organizations to deploy
2.1, the construction plans:
According to the characteristics of the project, reasonable arrangements for the installation of construction personnel, in accordance with the "before you get on, after the first branch in charge, after the first trunk extension, after the first pre-install" principle, the implementation of plane partitions, construction of interchange operations flow. In order to decoration and other construction professionals to provide sub-surface operations, particularly before the construction of terrazzo floor, the installation must be completed pipeline laying the ground, wearing floor and ceiling to install pipes and other construction within the installation