八里店鎮升山片標準廠房28#臨時用電施工組織設計.doc
進入下載頁
臨時用電施工組織設計
工程名稱 八里店鎮**標準廠房
四標段28#樓 工程地點 八里店鎮**曹報村
建筑面積(M2) 11811.6 建筑高度(M) 14.2 開工日期 2005.8.25
施工現場勘測情況(現場的地形、地貌,正式工程的位置,建筑材料、器具堆放位置,生產、生活暫設建筑物位置,用電設備裝設位置,現場周圍環境等):
本工程落址于八里店鎮**曹報村,東臨空地,南臨公寓、西臨空地、北臨27#樓。建筑物東西長108米,南北寬36米、結構層次三層,結構類型框架結構,平面呈長方形。施工現場建筑材料按平面布置圖堆放。木工制作及模板堆放在建筑物中間的西北面,鋼筋制作場及堆放在建筑物東北面;攪拌機、水泥罐、黃砂、碎石、磚堆放場等材料堆放在建筑北面。QTZ40T/M安裝在建筑物北面。鋼筋機械、電焊機、圓盤機等各機械擺放在鋼筋、模板制作場地。生活設施:民工宿舍、食堂、男、女廁所、淋浴室暫時設置在施工現場外面的西面。傳達室設置東北面,倉庫、辦公室設置在建筑物西北面,施工現場的總配電箱安裝在建筑物西北面,1#、2#、3#、4#、5#、6#、7#動力分電箱和1#、2#、3#照明分配電箱,各箱安裝在各機械設備旁。建筑物四周用磚圍墻圍護,進出主入口設置在東面,現場施工用電具體詳見表四、表七、表十一、
Design of the temporary use of Electricity
Project Name Zhen ** standard factory Bali
4 Lot 28 # Building Project site reports Pali village Cao Zhen **
Floor area (M2) 11811.6 building height (M) 14.2 start date 2005.8.25
Surveying the construction site conditions (site topography, the official position of the project, building materials, appliances stacked position, production and life of temporary building location, location of electrical equipment installation, on-site environment, etc.):
This project off the site in the North reportedly Cao Zhen ** village, east of the open space, apartment south west open space, bounded by 27 # floor. Building 108 meters from east to west, north and south 36 meters wide, three-level structure, the structure type of frame structure, flat rectangular. The construction site of building materials stacked by floor plans. Wood production and templates stacked in the middle of the northwest building, steel production and the stacked field northeast of the building; mixer, cement tanks, yellow sand, gravel, bricks and other material stacked in storage field construction north. QTZ40T / M installed in the building north. Steel machinery, welding, machine and other mechanical disc placed in the steel, the template-production. Living facilities: migrant workers dormitories, canteens, men, ladies room, shower room being set up at the construction site outside of the west. Janitor's room set the northeast, warehouses, office buildings set in the northwest, the construction site of the main distribution box installed in the building north-west, 1 #, 2 #, 3 #, 4 #, 5 #, 6 #, 7 # Power Distribution box and 1 #, 2 #, 3 # lighting electrical distribution box, the box next to mechanical equipment installed in each. Brick wall around the building envelope, and out of the main entrances to the east, on-site Construction Power specific see Table 4, Table 7, Table 11,